27INR0611 · BESS · Brazoria County
Bodkin BESS SLF
Bodkin BESS SLF is a 0 MW battery storage project in Brazoria County, Texas, connecting at The 138kV Danbury Dab DANBUR_POI_8 (BUS#42875) Station. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0611
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- Bodkin BESS, LLC
- Projected COD
- 12/01/2027
- Entered queue
- 03/23/2026
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Entered the queue with 0 MW, projected COD 12/01/2027
- 03/23/2026Screening → FIS Requested