23INR0054 · Solar · Brazoria County
Tanglewood Solar
Tanglewood Solar is a 251 MW solar project in Brazoria County, Texas, connecting at 345kV Seabreeze Substation. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/30/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0054
- Capacity
- 251 MW
- Fuel
- Solar (PV)
- Substation
- 345kV Seabreeze Substation
- County
- Brazoria County
- Interconnecting entity
- Brazoria Solar, LLC
- Projected COD
- 09/30/2026
- Entered queue
- 07/10/2020
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/20/2025Energization Approved → Sync Approved
- 08/05/2025IA Signed → Energization Approved
- 06/03/2024FIS Requested → FIS Approved
- 11/01/2022FIS Approved → IA Signed
- 11/24/2020Screening → FIS Requested
- 07/10/2020Entered the queue with 251 MW, projected COD 09/30/2026