LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0054 · Solar · Brazoria County

Tanglewood Solar

Tanglewood Solar is a 251 MW solar project in Brazoria County, Texas, connecting at 345kV Seabreeze Substation. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0054
Capacity
251 MW
Fuel
Solar (PV)
Interconnecting entity
Brazoria Solar, LLC
Projected COD
09/30/2026
Entered queue
07/10/2020
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/20/2025
    Energization Approved → Sync Approved
  • 08/05/2025
    IA Signed → Energization Approved
  • 06/03/2024
    FIS Requested → FIS Approved
  • 11/01/2022
    FIS Approved → IA Signed
  • 11/24/2020
    Screening → FIS Requested
  • 07/10/2020
    Entered the queue with 251 MW, projected COD 09/30/2026

Other projects at this substation

No other projects at this substation.