ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0194 · BESS · Brazoria County

Pequin Energy Storage

Pequin Energy Storage is a 103 MW battery storage project in Brazoria County, Texas, connecting at 39500 TN West Columbia 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/13/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0194
Capacity
103 MW
Fuel
BESS (BA)
Interconnecting entity
Pequin Energy Storage, LLC
Projected COD
09/13/2027
Entered queue
01/25/2021
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/14/2021
    Screening → FIS Requested
  • 01/25/2021
    Entered the queue with 103 MW, projected COD 09/13/2027

Other projects at this substation

No other projects at this substation.