LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Brazoria County

9.99 MW 50 MWh battery energy storage project connecting at 12.47kV Damon (DA) substation.

1 active project totalling 10 MW is queued to connect at 9.99 MW 50 MWh battery energy storage project connecting at 12.47kV Damon (DA) substation. in Brazoria County, Texas, according to ERCOT's October 2026 report.

Active capacity
10 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
47 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
23INR0603Damon BESS 2BESS10IA Signed08/21/20270