23INR0150 · Solar · Brazoria County
Cradle Solar
Cradle Solar is a 201 MW solar project in Brazoria County, Texas, connecting at tap 345kV 42500 Dow - 43035 Oasis ckt 18. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0150
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 42500 Dow - 43035 Oasis ckt 18
- County
- Brazoria County
- Interconnecting entity
- Cradle Solar LLC
- Projected COD
- 09/17/2027
- Entered queue
- 02/04/2021
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/14/2025FIS Requested → FIS Approved
- 03/15/2023FIS Approved → IA Signed
- 03/15/2021Screening → FIS Requested
- 02/04/2021Entered the queue with 201 MW, projected COD 09/17/2027