ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0150 · Solar · Brazoria County

Cradle Solar

Cradle Solar is a 201 MW solar project in Brazoria County, Texas, connecting at tap 345kV 42500 Dow - 43035 Oasis ckt 18. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0150
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Cradle Solar LLC
Projected COD
09/17/2027
Entered queue
02/04/2021
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/14/2025
    FIS Requested → FIS Approved
  • 03/15/2023
    FIS Approved → IA Signed
  • 03/15/2021
    Screening → FIS Requested
  • 02/04/2021
    Entered the queue with 201 MW, projected COD 09/17/2027

Other projects at this substation

No other projects at this substation.