20INR0248 · Solar · Brazoria County
DAMAZO (Second Division) SOLAR
DAMAZO (Second Division) SOLAR is a 100 MW solar project in Brazoria County, Texas, connecting at Tap 138 kV SANBER_POI_8 (Bus# 43110) to WEST COLUMBIA (Bus# 43380) Ckt 60 Line. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2025.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0248
- Capacity
- 100 MW
- Fuel
- Solar (PV)
- County
- Brazoria County
- Interconnecting entity
- TX Gulf Solar 1 LLC
- Projected COD
- 12/31/2025
- Entered queue
- 03/28/2019
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/17/2024Energization Approved → Sync Approved
- 10/08/2024IA Signed → Energization Approved
- 10/28/2022FIS Requested → FIS Approved
- 10/14/2020FIS Approved → IA Signed
- 07/29/2019Screening → FIS Requested
- 03/28/2019Entered the queue with 100 MW, projected COD 12/31/2025