Counties / Texas
Harris County power projects
Harris County, Texas has 33 active power projects totalling 6,844 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 6,243 MW (91%). The largest single project is Hobby BESS I (603 MW battery storage). 11 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
33
6.8 GW capacity
IA signed or later
11
33% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
5
since Sep 2026
Changes in Harris County
New
10/01/2026
Hockley BESS · BESS · Harris County
Entered the queue at 30.021619, -95.846315. Projected COD 03/01/2027.
+10 MW
COD change
10/01/2026
Rex Storage · BESS · Harris County
Projected COD moved 09/15/2027 → 10/30/2028. Delay #1 for this project.
+14 mo
COD change
10/01/2026
Bluegill BESS · BESS · Harris County
Projected COD moved 10/31/2027 → 10/31/2028. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Callisto II Energy Center · BESS · Harris County
Projected COD moved 10/01/2026 → 12/17/2026. Delay #1 for this project.
+3 mo
COD change
10/01/2026
Little York BESS · BESS · Harris County
Projected COD moved 07/27/2026 → 11/12/2026. Delay #1 for this project.
+4 mo
All projects
For residents and landowners
- What power projects are planned in Harris County?
- ERCOT's October 2026 report lists 33 active projects in Harris County totalling 6,844 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.