27INR0436 · BESS · Harris County
Coati Energy Storage
Coati Energy Storage is a 203 MW battery storage project in Harris County, Texas, connecting at Bus # 40830, Humble, 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0436
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- Substation
- Bus # 40830, Humble, 138 kV
- County
- Harris County
- Interconnecting entity
- PowerPulse LLC
- Projected COD
- 06/15/2029
- Entered queue
- 12/19/2024
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/21/2025Screening → FIS Requested
- 12/19/2024Entered the queue with 203 MW, projected COD 06/15/2029
Other projects at this substation
No other projects at this substation.