26INR0503 · BESS · Harris County
Rex Storage
COD delayed 1×
Rex Storage is a 256 MW battery storage project in Harris County, Texas, connecting at Tap 138 kV 48096 El Dorado - 43610 Scarsdale CKT 92. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/30/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0503
- Capacity
- 256 MW
- Fuel
- BESS (BA)
- County
- Harris County
- Interconnecting entity
- Rex BESS, LLC
- Projected COD
- 10/30/2028
- Entered queue
- 06/04/2024
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/15/2027 → 10/30/2028 (+14 months)
- 06/04/2024Entered the queue with 256 MW, projected COD 09/15/2027
- 06/04/2024Screening → FIS Requested