LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0548 · BESS · Harris County

Burnet Bay Storage

Burnet Bay Storage is a 208 MW battery storage project in Harris County, Texas, connecting at tap 138kV 40390 Crosby - 40790 Haney. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 06/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0548
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
TOCE TX BESS 4, LLC
Projected COD
06/01/2029
Entered queue
08/29/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/17/2026
    FIS Requested → FIS Approved
  • 08/29/2024
    Entered the queue with 208 MW, projected COD 06/01/2029
  • 08/29/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.