26INR0343 · BESS · Harris County
Stinger Energy Storage
Stinger Energy Storage is a 201 MW battery storage project in Harris County, Texas, connecting at Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0343
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Harris County
- Interconnecting entity
- Stinger Energy Storage LLC
- Projected COD
- 03/01/2028
- Entered queue
- 11/02/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/02/2023Entered the queue with 201 MW, projected COD 03/01/2028
- 11/02/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.