23INR0040 · Solar · Harris County
Dori BQ Solar
Dori BQ Solar is a 50 MW solar project in Harris County, Texas, connecting at tap 138kV 47210 Holmes – 42680 Garden Villas. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0040
- Capacity
- 50 MW
- Fuel
- Solar (PV)
- County
- Harris County
- Interconnecting entity
- Sunnyside Energy, LLC
- Projected COD
- 08/30/2027
- Entered queue
- 06/09/2020
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/01/2022FIS Requested → IA Signed
- 01/29/2021Screening → FIS Requested
- 06/09/2020Entered the queue with 50 MW, projected COD 08/30/2027