ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0317 · BESS · Harris County

Pinnacle Point Energy Storage

Pinnacle Point Energy Storage is a 101 MW battery storage project in Harris County, Texas, connecting at Tap Highlands (Bus # 40812) - HANEY ( BUS # 40790) 138 kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 07/10/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0317
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
GCI Pinnacle Point, LLC
Projected COD
07/10/2029
Entered queue
11/08/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/10/2025
    FIS Requested → FIS Approved
  • 11/08/2023
    Entered the queue with 101 MW, projected COD 07/10/2029
  • 11/08/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.