ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Harris County

Tap Highlands (Bus # 40812) - HANEY ( BUS # 40790) 138 kV

1 active project totalling 101 MW is queued to connect at Tap Highlands (Bus # 40812) - HANEY ( BUS # 40790) 138 kV in Harris County, Texas, according to ERCOT's October 2026 report.

Active capacity
101 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
26INR0317Pinnacle Point Energy StorageBESS101FIS Approved07/10/20290