LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0545 · BESS · Harris County

Knight Airport BESS I

Knight Airport BESS I is a 522 MW battery storage project in Harris County, Texas, connecting at Tap 138kV 48126 Gulfgate - 48199 Knight 06 and 42680 Garden Villas - 42770 Ashville 06. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0545
Capacity
522 MW
Fuel
BESS (BA)
Interconnecting entity
Airport Storage I LLC
Projected COD
10/15/2027
Entered queue
08/08/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/08/2024
    Entered the queue with 522 MW, projected COD 10/15/2027
  • 08/08/2024
    Screening → FIS Requested

Other projects at this substation