LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0382 · BESS · Harris County

Outer Loop BESS

Outer Loop BESS is a 201 MW battery storage project in Harris County, Texas, connecting at 40700 Greens Bayou 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/06/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0382
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Black Mountain Energy Storage II
Projected COD
12/06/2027
Entered queue
09/29/2021
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/19/2022
    Screening → FIS Requested
  • 09/29/2021
    Entered the queue with 201 MW, projected COD 12/06/2027

Other projects at this substation

No other projects at this substation.