Pez Rojo BESS

Pez Rojo BESS is a 217 MW battery storage project in Harris County, Texas, connecting at Tap 138 kV #40260 Chamon - #40912 King. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0245
Capacity
217 MW
Fuel
BESS (BA)
Interconnecting entity
Pez Rojo BESS, LLC
Projected COD
02/01/2029
Entered queue
06/14/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/01/2026
    FIS Requested → IA Signed
  • 06/14/2024
    Entered the queue with 217 MW, projected COD 02/01/2029
  • 06/14/2024
    Screening → FIS Requested