24INR0584 · BESS · Harris County

Kegans BESS (Houston IV BESS)

Kegans BESS (Houston IV BESS) is a 165 MW battery storage project in Harris County, Texas, connecting at 44140 CLODINE 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/05/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0584
Capacity
165 MW
Fuel
BESS (BA)
Interconnecting entity
SMT Houston IV LLC
Projected COD
09/05/2026
Entered queue
06/27/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/08/2026
    Energization Approved → Sync Approved
  • 05/06/2026
    IA Signed → Energization Approved
  • 07/01/2025
    FIS Requested → FIS Approved
  • 11/07/2024
    FIS Approved → IA Signed
  • 06/27/2023
    Entered the queue with 165 MW, projected COD 09/05/2026
  • 06/27/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.