LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Navarro County power projects

Navarro County, Texas has 26 active power projects totalling 4,255 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,733 MW (64%). The largest single project is Tehuacana Creek Solar (505 MW solar). 11 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
26
4.3 GW capacity
IA signed or later
11
42% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Navarro County

COD change
10/01/2026
Armadillo Solar · Solar · Navarro County
Projected COD moved 12/04/2026 → 12/31/2026. Delay #1 for this project.
+1 mo
COD change
10/01/2026
Wensowitch Solar · Solar · Navarro County
Projected COD moved 09/18/2028 → 04/17/2029. Delay #1 for this project.
+7 mo
COD change
10/01/2026
Elm Flats Solar SLF · Solar · Navarro County
Projected COD moved 09/30/2027 → 11/01/2027. Delay #1 for this project.
+1 mo
COD change
10/01/2026
Elm Flats Storage SLF · BESS · Navarro County
Projected COD moved 09/30/2027 → 11/01/2027. Delay #1 for this project.
+1 mo

All projects

ProjectFuelMWSubstationStageCOD
Tehuacana Creek SolarSolar505Tap 345kV 3381 Big Brown – 68091 Navarro circuitIA Signed05/18/2027
Wildflower StorageBESS359Drane switch #3295FIS Requested09/30/2028
TORMES SOLARSolar357tap 345kV 1906 Venus - 68091 NavarroIA Signed03/31/2027
Board Creek WindWind299345kV 3386 Outlaw SwitchSync Approved10/31/2026
Yellow Cat WindWind262tap 345kV 1906 Venus - 68091 NavarroIA Signed03/05/2027
Oak Valley SolarSolar25168091 (Navarro) (345)FIS Requested09/28/2029
Goodalta SolarSolar221tap 138kV 3127 Trinidad - 212 WinklerFIS Approved09/20/2027
Glasgow SolarSolar204Tap 345kV #2466 Big Onion - #68091 NavarroIA Signed03/16/2028
Bluebonnet Prairie WindWind180Tap 138kV 200 CHATFIELD - 3454 MONTFTSS__8IA Signed07/15/2028
Armadillo SolarSolar1503387 Revolution 138kVEnergization Approved12/31/2026
Cape Rich BESSBESS1503387 Revolution Switch 138kVIA Signed04/18/2030
Ponferrada SolarSolar149Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8FIS Requested04/06/2029
Wensowitch SolarSolar146Tapping 138 kV line Telico (192) to Montfort Switch (3454)FIS Approved04/17/2029
Elm Flats Solar SLFSolar126Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8IA Signed11/01/2027
Santa Monica SolarSolar106Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2FIS Approved09/20/2028
Pisgah Ridge Solar 2Solar102Tap 345kV 68091 Navarro - 46020 LimestoneFIS Requested03/31/2029
Kennedy SolarSolar102Tap 345kV 68040 Kopprl Capacitor Yard - 68091 NavarroFIS Requested12/31/2028
Pisgah Ridge Storage 3BESS101Tap 345kV 68091 Navarro - 46020 LimestoneFIS Requested03/31/2029
Glasgow StorageBESS101Tap 345kV #2466 Big Onion - #68091 NavarroIA Signed03/16/2028
Main Horn SolarSolar1003387 Revolution 138 KVFIS Requested09/17/2029
Hector SolarSolar82Haney (213) - Hubbard_8 (3515) 138kV LineScreening10/08/2028
Eytcheson Ranches SolarSolar76Tap 69kV 186 Navarro Mills – 107 Prairie HillFIS Requested01/01/2028
Whistle SolarSolar56Tap 138kV 213 Haney – 3478 NavarroFIS Requested05/15/2028
Hector StorageBESS43Haney (213) - Hubbard_8 (3515) 138kV LineFIS Requested10/08/2028
Kennedy StorageBESS25Tap 345kV 68040 Kopprl Capacitor Yard - 68091 NavarroFIS Requested12/31/2028
Elm Flats Storage SLFBESS0Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8IA Signed11/01/2027
Three Canes SolarSolar334Not listedWithdrawnn/a
Alliance SolarSolar180Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Navarro County?
ERCOT's October 2026 report lists 26 active projects in Navarro County totalling 4,255 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.