24INR0256 · Solar · Navarro County
Kennedy Solar
Kennedy Solar is a 102 MW solar project in Navarro County, Texas, connecting at Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0256
- Capacity
- 102 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Kennedy Bypass Solar LLC
- Projected COD
- 12/31/2028
- Entered queue
- 03/07/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/29/2022Screening → FIS Requested
- 03/07/2022Entered the queue with 102 MW, projected COD 12/31/2028