24INR0256 · Solar · Navarro County

Kennedy Solar

Kennedy Solar is a 102 MW solar project in Navarro County, Texas, connecting at Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0256
Capacity
102 MW
Fuel
Solar (PV)
Interconnecting entity
Kennedy Bypass Solar LLC
Projected COD
12/31/2028
Entered queue
03/07/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/29/2022
    Screening → FIS Requested
  • 03/07/2022
    Entered the queue with 102 MW, projected COD 12/31/2028

Other projects at this substation

Kennedy StorageBESS25 MWFIS Requested