LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Navarro County

Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro

2 active projects totalling 127 MW are queued to connect at Tap 345kV 68040 Kopprl Capacitor Yard - 68091 Navarro in Navarro County, Texas, according to ERCOT's October 2026 report.

Active capacity
127 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0256Kennedy SolarSolar102FIS Requested12/31/20280
24INR0391Kennedy StorageBESS25FIS Requested12/31/20280