26INR0130 · Solar · Navarro County
Elm Flats Solar SLF
COD delayed 1×
Elm Flats Solar SLF is a 126 MW solar project in Navarro County, Texas, connecting at Tap 138kV 3472 BRIAR_CRK_8 – 3467 POWELL1_8. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/01/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0130
- Capacity
- 126 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Orca Falls Solar, LLC
- Projected COD
- 11/01/2027
- Entered queue
- 06/13/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/30/2027 → 11/01/2027 (+1 months)
- 11/21/2025FIS Requested → IA Signed
- 06/13/2023Entered the queue with 126 MW, projected COD 09/30/2027
- 06/13/2023Screening → FIS Requested
Other projects at this substation
| Elm Flats Storage SLF | BESS | 0 MW | IA Signed |