Glasgow Solar
Glasgow Solar is a 204 MW solar project in Navarro County, Texas, connecting at Tap 345kV #2466 Big Onion - #68091 Navarro. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/16/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0206
- Capacity
- 204 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Glasgow Solar LLC
- Projected COD
- 03/16/2028
- Entered queue
- 01/12/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/08/2023FIS Requested → IA Signed
- 01/12/2022Entered the queue with 204 MW, projected COD 03/16/2028
- 01/12/2022Screening → FIS Requested