28INR0292 · BESS · Navarro County

Wildflower Storage

Wildflower Storage is a 359 MW battery storage project in Navarro County, Texas, connecting at Drane switch #3295. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0292
Capacity
359 MW
Fuel
BESS (BA)
Interconnecting entity
Wildflower Storage LLC
Projected COD
09/30/2028
Entered queue
05/15/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/15/2025
    Entered the queue with 359 MW, projected COD 09/30/2028
  • 05/15/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.