LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
21INR0421 · Solar · Navarro County

Armadillo Solar

COD delayed 1×

Armadillo Solar is a 150 MW solar project in Navarro County, Texas, connecting at 3387 Revolution 138kV. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
21INR0421
Capacity
150 MW
Fuel
Solar (PV)
Interconnecting entity
Armadillo Solar Center, LLC
Projected COD
12/31/2026
Entered queue
08/28/2019
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/04/2026 → 12/31/2026 (+1 months)
  • 07/27/2026
    IA Signed → Energization Approved
  • 10/08/2025
    FIS Requested → FIS Approved
  • 02/02/2021
    FIS Approved → IA Signed
  • 08/28/2019
    Entered the queue with 150 MW, projected COD 12/04/2026
  • 08/28/2019
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.