21INR0421 · Solar · Navarro County
Armadillo Solar
COD delayed 1×
Armadillo Solar is a 150 MW solar project in Navarro County, Texas, connecting at 3387 Revolution 138kV. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0421
- Capacity
- 150 MW
- Fuel
- Solar (PV)
- Substation
- 3387 Revolution 138kV
- County
- Navarro County
- Interconnecting entity
- Armadillo Solar Center, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 08/28/2019
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 12/04/2026 → 12/31/2026 (+1 months)
- 07/27/2026IA Signed → Energization Approved
- 10/08/2025FIS Requested → FIS Approved
- 02/02/2021FIS Approved → IA Signed
- 08/28/2019Entered the queue with 150 MW, projected COD 12/04/2026
- 08/28/2019Screening → FIS Requested
Other projects at this substation
No other projects at this substation.