26INR0180 · BESS · Navarro County

Cape Rich BESS

Cape Rich BESS is a 150 MW battery storage project in Navarro County, Texas, connecting at 3387 Revolution Switch 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/18/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0180
Capacity
150 MW
Fuel
BESS (BA)
Interconnecting entity
Cape Rich BESS
Projected COD
04/18/2030
Entered queue
07/03/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/03/2025
    FIS Approved → IA Signed
  • 06/26/2024
    FIS Requested → FIS Approved
  • 07/03/2023
    Entered the queue with 150 MW, projected COD 04/18/2030
  • 07/03/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.