28INR0182 · Solar · Navarro County
Ponferrada Solar
Ponferrada Solar is a 149 MW solar project in Navarro County, Texas, connecting at Tap 138 KV 3456 CORSWEST1_8 - 3457 CORS_MOBT_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/06/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0182
- Capacity
- 149 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Karol Solar VI
- Projected COD
- 04/06/2029
- Entered queue
- 10/01/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/15/2025Screening → FIS Requested
- 10/01/2024Entered the queue with 149 MW, projected COD 04/06/2029
Other projects at this substation
No other projects at this substation.