24INR0205 · Solar · Navarro County
Wensowitch Solar
COD delayed 1×
Wensowitch Solar is a 146 MW solar project in Navarro County, Texas, connecting at Tapping 138 kV line Telico (192) to Montfort Switch (3454). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/17/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0205
- Capacity
- 146 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Greenalia Solar Power Wensowitch LLC
- Projected COD
- 04/17/2029
- Entered queue
- 01/07/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/18/2028 → 04/17/2029 (+7 months)
- 01/09/2026FIS Requested → FIS Approved
- 07/25/2022Screening → FIS Requested
- 01/07/2022Entered the queue with 146 MW, projected COD 09/18/2028
Other projects at this substation
No other projects at this substation.