LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0205 · Solar · Navarro County

Wensowitch Solar

COD delayed 1×

Wensowitch Solar is a 146 MW solar project in Navarro County, Texas, connecting at Tapping 138 kV line Telico (192) to Montfort Switch (3454). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/17/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0205
Capacity
146 MW
Fuel
Solar (PV)
Interconnecting entity
Greenalia Solar Power Wensowitch LLC
Projected COD
04/17/2029
Entered queue
01/07/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/18/2028 → 04/17/2029 (+7 months)
  • 01/09/2026
    FIS Requested → FIS Approved
  • 07/25/2022
    Screening → FIS Requested
  • 01/07/2022
    Entered the queue with 146 MW, projected COD 09/18/2028