28INR0335 · Solar · Navarro County
Oak Valley Solar
Oak Valley Solar is a 251 MW solar project in Navarro County, Texas, connecting at 68091 (Navarro) (345). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/28/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0335
- Capacity
- 251 MW
- Fuel
- Solar (PV)
- Substation
- 68091 (Navarro) (345)
- County
- Navarro County
- Interconnecting entity
- Oak Valley Solar LLC
- Projected COD
- 09/28/2029
- Entered queue
- 03/19/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/19/2025Entered the queue with 251 MW, projected COD 09/28/2029
- 03/19/2025Screening → FIS Requested