Counties / Texas

Matagorda County power projects

Matagorda County, Texas has 24 active power projects totalling 5,583 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 2,415 MW (43%). The largest single project is STP Unit2 High Pressure Turbine Upgrade (1,336 MW other). 10 projects have signed an interconnection agreement or reached a later stage. 5 projects in the county are listed as withdrawn or cancelled.

Active projects
24
5.6 GW capacity
IA signed or later
10
42% of active projects
Withdrawn or cancelled
5
listed by ERCOT
Changes tracked
5
since Sep 2026

Changes in Matagorda County

COD change
10/01/2026
Pavlov BESS2 · BESS · Matagorda County
Projected COD moved 08/29/2026 → 12/13/2026. Delay #1 for this project.
+3 mo
Withdrawn
09/14/2026
Charolais Solar · Solar · Matagorda County
Listed as cancelled by ERCOT.
−262 MW
Withdrawn
09/14/2026
Razorbill Solar · Solar · Matagorda County
Listed as cancelled by ERCOT.
−240 MW
Withdrawn
09/14/2026
Charolais Storage · BESS · Matagorda County
Listed as cancelled by ERCOT.
−150 MW
Withdrawn
09/14/2026
Razorbill Storage · BESS · Matagorda County
Listed as cancelled by ERCOT.
−120 MW

All projects

ProjectFuelMWSubstationStageCOD
STP Unit2 High Pressure Turbine UpgradeOther1,3365915 SO_TEX__345A 345 kVFIS Requested04/23/2027
Duffy SolarSolar502Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39)IA Signed12/31/2027
Bluefox Solar 1Solar403#8754 Zoisite 345kVFIS Requested05/31/2029
Bluefox Solar 2Solar402#8754 Zoisite 345kVFIS Requested01/17/2030
Peyton Creek Wind IIWind24142400 Refuge 345kVSync Approved12/31/2026
Duffy BESSBESS241Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39)IA Signed12/31/2026
Shoshana StorageBESS221Tap STP – Refuge ckt 27FIS Requested05/30/2028
Solar Star Bay City StorageBESS206Tap 138kV Conoco 8138 - Black Cat 80124FIS Requested02/27/2029
Running Iron SolarSolar205Tap 138kV Conoco 8138 - Black Cat 80124FIS Requested10/16/2028
Bluefox Solar 3Solar202#8754 Zoisite 345kVFIS Requested04/18/2030
Eldora BESSBESS201345 kV South Texas Project (Bus# 5915) – Hillje (Bus# 44200) Transmission Line Ckt 1IA Signed07/02/2028
Eldora SolarSolar201Tap 345 kV 5915 South Texas Project – 44200 Hillje Ckt 1IA Signed07/02/2028
Blackcat StorageBESS201138kV Blackcat Substation (#80124)FIS Requested12/31/2027
Percy Farm SolarSolar199Tap 345kV 8123 Blessing - 5915 STPFIS Requested05/31/2029
Bastion BESSBESS154Blessing Substation 138 kV (ID 8121)FIS Requested11/01/2028
Midfield PV Project SLFSolar150Tap 138kV 8121 Blessing - 8125 LolitaFIS Requested07/01/2028
City Breeze BESSBESS1438111 MAGILL4A 138KVIA Signed03/18/2027
Post Trail EnergyBESS104Tap 138kV Conoco 8138 - Black Cat 80124FIS Requested10/16/2028
Matagorda SolarSolar1015555 Shropshire 69kVIA Signed08/25/2027
Pledgor BESSBESS100Tap Gulftie (43340) – Pledger (43120) circuit 60FIS Approved04/06/2028
Isaac SolarSolar518114 Conoco 138kVIA Signed04/15/2027
Pavlov BESS2BESS10New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Pavlov TSP Station Code: PAVLOV Load Name: 138_13_1 Bus #: PTI Bus Number: 8608 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01IA Signed12/13/2026
Pledger BESSBESS1029.188382, -95.911558IA Signed11/04/2026
Midfield BESS Project SLFBESS0Tap 138kV 8121 Blessing - 8125 LolitaFIS Requested07/01/2028
Juanita Creek BESSBESS304Not listedWithdrawnn/a
Charolais SolarSolar262tap 345kV 44000 W A Parish - 5915 STPWithdrawn12/15/2026
Razorbill SolarSolar240tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64Withdrawn12/15/2027
Charolais StorageBESS150tap 345kV 44000 W A Parish - 5915 STPWithdrawn12/15/2026
Razorbill StorageBESS120tap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64Withdrawn12/15/2027

For residents and landowners

What power projects are planned in Matagorda County?
ERCOT's October 2026 report lists 24 active projects in Matagorda County totalling 5,583 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.