20INR0155 · Wind · Matagorda County

Peyton Creek Wind II

Peyton Creek Wind II is a 241 MW wind project in Matagorda County, Texas, connecting at 42400 Refuge 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0155
Capacity
241 MW
Fuel
Wind (WT)
Interconnecting entity
RWE Renewables Development, LLC
Projected COD
12/31/2026
Entered queue
08/21/2018
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/29/2026
    FIS Approved → IA Signed
  • 02/05/2025
    Energization Approved → Sync Approved
  • 12/30/2024
    IA Signed → Energization Approved
  • 06/25/2024
    FIS Requested → FIS Approved
  • 03/14/2019
    Screening → FIS Requested
  • 08/21/2018
    Entered the queue with 241 MW, projected COD 12/31/2026