ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Matagorda County

42400 Refuge 345kV

1 active project totalling 241 MW is queued to connect at 42400 Refuge 345kV in Matagorda County, Texas, according to ERCOT's October 2026 report.

Active capacity
241 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
20INR0155Peyton Creek Wind IIWind241Sync Approved12/31/20260