26INR0429 · BESS · Matagorda County
Post Trail Energy
Post Trail Energy is a 104 MW battery storage project in Matagorda County, Texas, connecting at Tap 138kV Conoco 8138 - Black Cat 80124. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/16/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0429
- Capacity
- 104 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV Conoco 8138 - Black Cat 80124
- County
- Matagorda County
- Interconnecting entity
- Post Trail Energy, LLC
- Projected COD
- 10/16/2028
- Entered queue
- 08/26/2024
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/26/2024Entered the queue with 104 MW, projected COD 10/16/2028
- 08/26/2024Screening → FIS Requested
Other projects at this substation
| Running Iron Solar | Solar | 205 MW | FIS Requested |
| Solar Star Bay City Storage | BESS | 206 MW | FIS Requested |