25INR0604 · BESS · Matagorda County

Pledger BESS

Pledger BESS is a 9.5 MW battery storage project in Matagorda County, Texas, connecting at 29.188382, -95.911558. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/04/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0604
Capacity
9.5 MW
Fuel
BESS (BA)
Interconnecting entity
Regis Pledger LLC
Projected COD
11/04/2026
Entered queue
04/29/2024
ERCOT zone
COASTAL
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/29/2024
    Entered the queue with 9.5 MW, projected COD 11/04/2026
  • 04/29/2024
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.