ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0057 · Solar · Matagorda County

Duffy Solar

Duffy Solar is a 502 MW solar project in Matagorda County, Texas, connecting at Tap 345kV WAP to STP CKT39 (PTI# 5915-44000 CKT 39). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0057
Capacity
502 MW
Fuel
Solar (PV)
Interconnecting entity
Duffy Project Co LLC
Projected COD
12/31/2027
Entered queue
09/11/2020
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/12/2023
    FIS Requested → IA Signed
  • 02/04/2021
    Screening → FIS Requested
  • 09/11/2020
    Entered the queue with 502 MW, projected COD 12/31/2027

Other projects at this substation

Duffy BESSBESS241 MWIA Signed