24INR0337 · Solar · Matagorda County
Eldora Solar
Eldora Solar is a 201 MW solar project in Matagorda County, Texas, connecting at Tap 345 kV 5915 South Texas Project – 44200 Hillje Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/02/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0337
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Matagorda County
- Interconnecting entity
- Eldora Energy LLC
- Projected COD
- 07/02/2028
- Entered queue
- 06/01/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/15/2023FIS Requested → IA Signed
- 06/01/2022Entered the queue with 201 MW, projected COD 07/02/2028
- 06/01/2022Screening → FIS Requested