LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0020 · Solar · Matagorda County

Percy Farm Solar

Percy Farm Solar is a 199 MW solar project in Matagorda County, Texas, connecting at Tap 345kV 8123 Blessing - 5915 STP. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0020
Capacity
199 MW
Fuel
Solar (PV)
Interconnecting entity
Percy Farm Solar 1, LLC
Projected COD
05/31/2029
Entered queue
03/16/2021
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/21/2021
    Screening → FIS Requested
  • 03/16/2021
    Entered the queue with 199 MW, projected COD 05/31/2029

Other projects at this substation

No other projects at this substation.