28INR0341 · BESS · Matagorda County

Bastion BESS

Bastion BESS is a 154 MW battery storage project in Matagorda County, Texas, connecting at Blessing Substation 138 kV (ID 8121). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0341
Capacity
154 MW
Fuel
BESS (BA)
Interconnecting entity
BESS BASTION LLC
Projected COD
11/01/2028
Entered queue
06/19/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/19/2025
    Entered the queue with 154 MW, projected COD 11/01/2028
  • 06/19/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.