26INR0714 · BESS · Matagorda County
Pavlov BESS2
COD delayed 1×
Pavlov BESS2 is a 10 MW battery storage project in Matagorda County, Texas, connecting at New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Pavlov TSP Station Code: PAVLOV Load Name: 138_13_1 Bus #: PTI Bus Number: 8608 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/13/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0714
- Capacity
- 10 MW
- Fuel
- BESS (BA)
- County
- Matagorda County
- Interconnecting entity
- Matagorda Clean Energy Center, LLC
- Projected COD
- 12/13/2026
- Entered queue
- 06/18/2025
- ERCOT zone
- COASTAL
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/29/2026 → 12/13/2026 (+3 months)
- 06/18/2025Entered the queue with 10 MW, projected COD 08/29/2026
- 06/18/2025Screening → IA Signed