LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0338 · BESS · Matagorda County

Eldora BESS

Eldora BESS is a 201 MW battery storage project in Matagorda County, Texas, connecting at 345 kV South Texas Project (Bus# 5915) – Hillje (Bus# 44200) Transmission Line Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/02/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0338
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Eldora Energy LLC
Projected COD
07/02/2028
Entered queue
06/01/2022
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/18/2023
    FIS Requested → FIS Approved
  • 11/15/2023
    FIS Approved → IA Signed
  • 06/01/2022
    Entered the queue with 201 MW, projected COD 07/02/2028
  • 06/01/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.