Deaf Smith County power projects
Deaf Smith County, Texas has 11 active power projects totalling 6,387 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 3,164 MW (50%). The largest single project is Aurelius 3 Natural Gas (1,275 MW natural gas). 5 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
11
6.4 GW capacity
IA signed or later
5
45% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
6
since Sep 2026
Changes in Deaf Smith County
COD change
10/01/2026
Aurelius 3 Natural Gas · Gas · Deaf Smith County
Projected COD moved 06/30/2029 → 06/30/2030. Delay #1 for this project.
+12 mo
COD change
10/01/2026
Aurelius 3 Wind · Wind · Deaf Smith County
Projected COD moved 03/31/2029 → 06/30/2030. Delay #1 for this project.
+15 mo
COD change
10/01/2026
Aurelius 3 Solar · Solar · Deaf Smith County
Projected COD moved 03/31/2029 → 06/30/2030. Delay #1 for this project.
+15 mo
COD change
10/01/2026
White Tail Solar · Solar · Deaf Smith County
Projected COD moved 09/21/2027 → 12/29/2028. Delay #1 for this project.
+15 mo
MW change
10/01/2026
705 → 497 MW
Stage change
09/17/2026
FIS Approved
All projects
For residents and landowners
- What power projects are planned in Deaf Smith County?
- ERCOT's October 2026 report lists 11 active projects in Deaf Smith County totalling 6,387 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.