Substation / point of interconnection ยท Deaf Smith County
23908 Deaf Smith station 345kV
2 active projects totalling 1,119 MW are queued to connect at 23908 Deaf Smith station 345kV in Deaf Smith County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,119 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0010 | Aurelius 2 Wind | Wind | 622 | FIS Requested | 09/30/2028 | 0 |
| 29INR0012 | Aurelius 3 Wind | Wind | 497 | FIS Requested | 06/30/2030 | 1 |