LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Deaf Smith County

Tap 345kV 23910 Windmill - 23906 AJ Swope

1 active project totalling 516 MW is queued to connect at Tap 345kV 23910 Windmill - 23906 AJ Swope in Deaf Smith County, Texas, according to ERCOT's October 2026 report.

Active capacity
516 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
20INR0255Renegade ProjectSolar516IA Signed01/15/20280