20INR0255 · Solar · Deaf Smith County
Renegade Project
Renegade Project is a 516 MW solar project in Deaf Smith County, Texas, connecting at Tap 345kV 23910 Windmill - 23906 AJ Swope. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0255
- Capacity
- 516 MW
- Fuel
- Solar (PV)
- County
- Deaf Smith County
- Interconnecting entity
- Renegade Renewable LLC
- Projected COD
- 01/15/2028
- Entered queue
- 02/07/2019
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/04/2021FIS Requested → IA Signed
- 02/07/2019Entered the queue with 516 MW, projected COD 01/15/2028
- 02/07/2019Screening → FIS Requested
Other projects at this substation
No other projects at this substation.