29INR0009 · Solar · Deaf Smith County
Aurelius 2 Solar
Aurelius 2 Solar is a 445 MW solar project in Deaf Smith County, Texas, connecting at 23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD).. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0009
- Capacity
- 445 MW
- Fuel
- Solar (PV)
- County
- Deaf Smith County
- Interconnecting entity
- IP Roman, LLC
- Projected COD
- 09/30/2028
- Entered queue
- 11/30/2023
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/10/2026FIS Requested → IA Signed
- 11/30/2023Entered the queue with 445 MW, projected COD 09/30/2028
- 11/30/2023Screening → FIS Requested
Other projects at this substation
| Aurelius 3 Solar | Solar | 445 MW | FIS Requested |