24INR0134 · BESS · Deaf Smith County

BRP Hemera BESS

BRP Hemera BESS is a 207 MW battery storage project in Deaf Smith County, Texas, connecting at 345 kV Deaf Smith Substation (#23908, Oncor). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0134
Capacity
207 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Hemera BESS LLC
Projected COD
12/01/2029
Entered queue
12/14/2021
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/14/2021
    Entered the queue with 207 MW, projected COD 12/01/2029
  • 12/14/2021
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.