Substation / point of interconnection ยท Deaf Smith County
23908 Deaf Smith station 345 kV
3 active projects totalling 3,021 MW are queued to connect at 23908 Deaf Smith station 345 kV in Deaf Smith County, Texas, according to ERCOT's October 2026 report.
Active capacity
3,021 MW
queued at this substation
Active projects
3
3 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0361 | Aurelius 3 Natural Gas | Gas | 1,275 | FIS Requested | 06/30/2030 | 1 |
| 29INR0003 | Aurelius Solar | Solar | 1,124 | IA Signed | 06/30/2028 | 0 |
| 29INR0004 | Aurelius Wind | Wind | 622 | IA Signed | 06/30/2028 | 0 |