29INR0361 · Gas · Deaf Smith County
Aurelius 3 Natural Gas
COD delayed 1×
Aurelius 3 Natural Gas is a 1,275 MW natural gas project in Deaf Smith County, Texas, connecting at 23908 Deaf Smith station 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0361
- Capacity
- 1,275 MW
- Fuel
- Gas (IC)
- Substation
- 23908 Deaf Smith station 345 kV
- County
- Deaf Smith County
- Interconnecting entity
- IP Roman III Gas, LLC
- Projected COD
- 06/30/2030
- Entered queue
- 06/25/2026
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 06/30/2029 → 06/30/2030 (+12 months)
- 06/25/2026Entered the queue with 1,275 MW, projected COD 06/30/2029
- 06/25/2026Screening → FIS Requested
Other projects at this substation
| Aurelius Solar | Solar | 1,124 MW | IA Signed |
| Aurelius Wind | Wind | 622 MW | IA Signed |