Counties / Texas
Hill County power projects
Hill County, Texas has 22 active power projects totalling 7,763 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 4,053 MW (52%). The largest single project is Bullock Gas (1,400 MW natural gas). 11 projects have signed an interconnection agreement or reached a later stage. 5 projects in the county are listed as withdrawn or cancelled.
Active projects
22
7.8 GW capacity
IA signed or later
11
50% of active projects
Withdrawn or cancelled
5
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Hill County
Withdrawn
Unconfirmed
10/01/2026
Three W Solar · Solar · Hill County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−111 MW
COD change
10/01/2026
Compadre Solar · Solar · Hill County
Projected COD moved 07/31/2026 → 10/31/2026. Delay #1 for this project.
+3 mo
COD change
10/01/2026
Compadre Solar II · Solar · Hill County
Projected COD moved 10/01/2026 → 12/31/2026. Delay #1 for this project.
+3 mo
COD change
10/01/2026
Files BESS SLF · BESS · Hill County
Projected COD moved 12/31/2027 → 11/07/2029. Delay #1 for this project.
+22 mo
All projects
For residents and landowners
- What power projects are planned in Hill County?
- ERCOT's October 2026 report lists 22 active projects in Hill County totalling 7,763 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.