LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0166 · Solar · Hill County

Compadre Solar II

COD delayed 1×

Compadre Solar II is a 201 MW solar project in Hill County, Texas, connecting at Tap 345kV 68090 Sam Switch – 3389 Fort Smith. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0166
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Hill Solar II, LLC
Projected COD
12/31/2026
Entered queue
09/15/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2026 → 12/31/2026 (+3 months)
  • 07/16/2026
    Energization Approved → Sync Approved
  • 04/27/2026
    IA Signed → Energization Approved
  • 06/16/2025
    FIS Requested → FIS Approved
  • 12/24/2024
    FIS Approved → IA Signed
  • 03/07/2023
    Screening → FIS Requested
  • 09/15/2022
    Entered the queue with 201 MW, projected COD 10/01/2026

Other projects at this substation

No other projects at this substation.